Sheet 1: Option2

Option 2 - Maintain Existing Regime












Cost Item Item Description Assumptions Quantity Unit Rate Item Cost





Total Existing Maintenance £4,900
1 Relief Channel maintenance Machine and dumper for 4 days at £300 per day with 2 Operatives at £12 per hour (7.5 hour day) and remove debris from site. 1 Item 2,500 2,500
2 Culvert maintenance Machine and dumper for 4 days at £300 per day with 2 Operatives at £12 per hour (7.5 hour day). 1 Item 2,400 2,400





Annual Post Construction Maintenance Cost 4,900

Sheet 2: Option3a

Option 3a - Relief Channel Enlargement












Cost Item Item Description Assumptions Quantity Unit Rate Item Cost





Total Flood Storage Reservoir Cost £470,740
1 Excavate material for widening of existing channel and preparation of surface. Removal of 215 m3 required. Excavate and remove from site. 215 m3 12 2,580
2 Excavate material for widening of existing concrete channel and preparation of surface. Removal of 1065 m3 required. Excavate and remove from site. 1,065 m3 12 12,780
3 Removal of existing reinforced concrete channel. Removal of 241 m3 required. Excavate and remove from site. 241 m3 23 5,543
4 Tipping at Licensed tip. Tipping of excavated material to licensed tip. 1,521 m3 20 30,420
5 Construction of new concrete channel. 502 m3 of concrete required. Rate includes providing RMC and placing. 502 m3 64 32,128
6 Formwork for new concrete channel. Formwork rough finish for walls. 2,484 m2 41 101,844
7 Reinforcement for new concrete channel. Assume 1% steel from concrete volume required. 5 m3 of steel required. 39 tonne 250 9,750
8 Replacement of culvert. Assume 8 m length. Replace with Precast box culvert 2400 mm x 1800 mm installed by pipe gang and plant (£75 per m). 8 m 575 4,600
9 Install Headwalls Construct 2 No. headwalls to culvert. 1 Item 4,000 4,000
8 Localised bunding. Assume bunding required to protect properties on Barton and Herschel Road. 1 Item 20,000 20,000
8 Landscaping / Reinstatement Spread and Rotivate topsoil, reseed locations and miscellaneous. Assume 10m width at £1 per m2. 7,400 m2 1 7,400





Construction Cost 231,045
9 General Contingency Allow 25% of Construction Cost


57,761
10 General and Preliminary Items Allow 25%


72,202
11 Overhead and Profit Allow 15%


54,151





Relief Channel Enlargement Capital Works Cost 415,159
12 Relief Channel maintenance Machine and dumper for 4 days at £300 per day with 2 Operatives at £12 per hour (7.5 hour day) and remove debris from site. 1 Item 2,500 2,500





Annual Post Construction Maintenance Cost 2,500
13 Design Design at 10% of Construction Cost and General contingency. 1 Item 28,881 28,881
14 Supervision Cost Half time supervisor at £35 per hour for 16 weeks (18.75 hour week) and Project Manager at £40 per hour for 10 hours per week. 1 Item 16,900 16,900
15 Agency costs Project Manager at £40 per hour for 1 day (7.5 hour day) per week for 16 weeks. 1 Item 4,800 4,800
16 Planning Supervisor Services Allowance of £2500 (min for small scheme) 1 Item 2,500 2,500





Reservoir Design, Supervision and Agency Cost 53,081

Sheet 3: Option3b

Option 3b - Culvert Enlargement












Cost Item Item Description Assumptions Quantity Unit Rate Item Cost





Total Flood Storage Reservoir Cost £609,663
1 Remove existing culvert. Removal of 157 m required. Excavate and remove from site. Assume 3m depth to remove. 471 m3 18 8,478
2 Excavate material for new culvert Assume 3.4 m width x 3 m depth. 1,130 m3 12 13,560
3 Tipping at Licensed tip. Tipping of removed material to licensed tip. 1,601 m3 20 32,020
4 Fill material. Import fill material for box culvert base and surround 157 m length. 415 m3 14 5,810
5 Construction of new culvert. Precast box concrete culvert. Assume 2400 mm width x 1800 mm height for supply and delivery only. Installed by concrete pipe gang and plant 2.5-3.0m deep (£75 per m). 157 m 575 90,275
6 Construction of manholes. Provision of 2 No. manholes. Assume precast concrete 900 mm diameter at depth 1.5 m. 2 Nr 768 1,536
7 Install Headwalls and weedscreen. Construction of 2 No. headwalls and provision of weedscreen. 1 Item 5,000 5,000
8 Services interruption. Depending on locations. Allow for utility company costs of £1000 per utility. Assume 4 utilities are affected. 4 Item 1,000 4,000
9 Working around services. Supporting services. 1 Item 10,000 10,000
10 Replace footpath. Replace footpath 100 m length 3 m width. 300 m2 8 2,400
11 Replace Road. Replace road 57 m length 6 m width. 342 m2 12 4,104
12 Foul sewer. Assume 10,000 for temporarily diverting/moving foul sewer pipe. 1 Item 10,000 10,000

Localised bunding. Assume bunding required to protect properties on Barton and Herschel Road. 1 Item 20,000 20,000
13 Boundary walls and fencing. Replace boundary walls and fences. Assume 100 m length, fencing/walls both sides. 200 m 50 10,000
14 Landscaping / Reinstatement Spread and Rotivate topsoil, reseed locations and miscellaneous. Assume 10m width at £1 per m2. 1,570 m2 1 1,570
15 Difficult working. Difficult and tight working conditions between existing housing. Assume extra construction cost. 1 Item 90,275 90,275





Construction Cost 309,028
6 General Contingency Allow 25% of Construction Cost


77,257
7 General and Preliminary Items Allow 25%


96,571
8 Overhead and Profit Allow 15%


72,428





Culvert Enlargement Capital Works Cost 555,285
9 Culvert maintenance Machine and dumper for 4 days at £300 per day with 2 Operatives at £12 per hour (7.5 hour day). 1 Item 2,400 2,400





Annual Post Construction Maintenance Cost 2,400
10 Design Design at 10% of Construction Cost and General contingency. 1 Item 38,629 38,629
11 Supervision Cost Half time supervisor at £35 per hour for 8 weeks (18.75 hour week) and Project Manager at £40 per hour for 10 hours per week. 1 Item 8,450 8,450
12 Agency costs Project Manager at £40 per hour for 1 day (7.5 hour day) per week for 8 weeks. 1 Item 2,400 2,400
13 Planning Supervisor Services Allowance of £2500 (min for small scheme) 1 Item 2,500 2,500





Reservoir Design, Supervision and Agency Cost 51,979

Sheet 4: Option4a

Option 4a - Provision of Flood Storage Reservoir to 50 year standard of protection (Flood Defence Only)












Cost Item Item Description Assumptions Quantity Unit Rate Item Cost





Total Flood Storage Reservoir Cost £484,369
1 Excavate lagoon and use the material to construct surrounding embankments. 10,000m3 of storage required. Assume reservoir is outside floodplain. Excavate, Transport, Place and Compact at a rate of £10/m3. 10,000 m3 10 100,000
2 Inlet and Outlet Control Structures Assume 1 inlet and 1 outlet. All Headwalls in-situ concrete, fitted with penstock (for emergency closure or repair) and weedscreen. 1 Item 50,000 50,000
3 Emergency Spillway Assume 100m length spillway with width of 3m and scour protection. 1,000 m2 20 20,000
4 Construction of Culvert Assume 40m length. Precast concrete culvert 2.4 x 2.4m 40 m 1,000 40,000
5 Landscaping / Reinstatement Spread and Rotivate topsoil, reseed locations and miscellaneous. Allow 2m storage depth at £1 per m2. 5,000 m2 1 5,000
6 Services interruption Depending on locations. Allow for utility company costs of £1000 per utility. Assume 3 utilities are affected. 3 Item 1,000 3,000





Construction Cost 218,000
7 General Contingency Allow 25% of Construction Cost


54,500
8 General and Preliminary Items Allow 25%


68,125
9 Overhead and Profit Allow 15%


51,094





Storage Reservoir Capital Works Cost 391,719
10 Reservoir Maintenance Supervising Engineer at £50 per hour for 2 days ( 7.5 hour day). 15 hours 50 750
11 Grass cutting of reservoir and maintenance of control structures Tractor with side arm cutter, plus one hand held strimmer for 5 days at £200 per day. Together with 2 Operatives at £12 per hour (7.5 hour day). 1 Item 1,900 1,900





Annual Post Construction Maintenance Cost 2,650
12 Design Design at 10% of Construction Cost and General contingency. Plus Panel engineer at £65 per hour for 2 weeks (7.5 hour day) 1 Item 32,125 32,125
13 Supervision Cost Full time supervisor at £35 per hour for 24 weeks (37.5 hour week) and Project Manager at £40 per hour for 22.5 hours per week. Plus Panel Engineer at £65 per hour for 2 weeks (37.5 hour week). 1 Item 45,375 45,375
14 Agency costs Project Manager at £40 per hour for 2 days (7.5 hour day) per week for 10 weeks 1 Item 6,000 6,000
15 Planning Supervisor Services Allowance of £6500 1 Item 6,500 6,500





Reservoir Design, Supervision and Agency Cost 90,000

Sheet 5: Option4b

Option 4b - Provision of Flood Storage Reservoir to 100 year standard of portection (Flood Defence Only)












Cost Item Item Description Assumptions Quantity Unit Rate Item Cost





Total Flood Storage Reservoir Cost £585,267
1 Excavate lagoon and use the material to construct surrounding embankments. 15,000m3 of storage required. Assume reservoir is outside floodplain. Excavate, Transport, Place and Compact at a rate of £10/m3. 15,000 m3 10 150,000
2 Inlet and Outlet Control Structures Assume 1 inlet and 1 outlet. All Headwalls in-situ concrete, fitted with penstock (for emergency closure or repair) and weedscreen. 1 Item 50,000 50,000
3 Emergency Spillway Assume 100m length spillway with width of 3m and scour protection. 1,000 m2 20 20,000
4 Construction of Culvert Assume 40m length. Precast concrete culvert 2.4 x 2.4m 40 m 1,000 40,000
5 Landscaping / Reinstatement Spread and Rotivate topsoil, reseed locations and miscellaneous. Allow 2m storage depth at £1 per m2. 7,500 m2 1 7,500
6 Services interruption Depending on locations. Allow for utility company costs of £1000 per utility. Assume 3 utilities are affected. 3 Item 1,000 3,000





Construction Cost 270,500
7 General Contingency Allow 25% of Construction Cost


67,625
8 General and Preliminary Items Allow 25%


84,531
9 Overhead and Profit Allow 15%


63,398





Storage Reservoir Capital Works Cost 486,055
10 Reservoir Maintenance Supervising Engineer at £50 per hour for 2 days ( 7.5 hour day). 15 hours 50 750
11 Grass cutting of reservoir and maintenance of control structures Tractor with side arm cutter, plus one hand held strimmer for 5 days at £200 per day. Together with 2 Operatives at £12 per hour (7.5 hour day). 1 Item 1,900 1,900





Annual Post Construction Maintenance Cost 2,650
12 Design Design at 10% of Construction Cost and General contingency. Plus Panel engineer at £65 per hour for 2 weeks (7.5 hour day) 1 Item 38,688 38,688
13 Supervision Cost Full time supervisor at £35 per hour for 24 weeks (37.5 hour week) and Project Manager at £40 per hour for 22.5 hours per week. Plus Panel Engineer at £65 per hour for 2 weeks (37.5 hour week). 1 Item 45,375 45,375
14 Agency costs Project Manager at £40 per hour for 2 days (7.5 hour day) per week for 10 weeks 1 Item 6,000 6,000
15 Planning Supervisor Services Allowance of £6500 1 Item 6,500 6,500





Reservoir Design, Supervision and Agency Cost 96,563

Sheet 6: Option4c

Option 4c - Provision of Flood Storage Reservoir to 100 year standard and Wetland Area












Cost Item Item Description Assumptions Quantity Unit Rate Item Cost





Total Flood Storage Reservoir Cost £1,796,048
1 Excavate lagoon and use the material to construct surrounding embankments. 75,000m3 of storage required. Assume reservoir is outside floodplain. Excavate, Transport, Place and Compact at a rate of £10/m3. 75,000 m3 10 750,000
2 Inlet and Outlet Control Structures Assume 1 inlet and 1 outlet. All Headwalls in-situ concrete, fitted with penstock (for emergency closure or repair) and weedscreen. 1 Item 50,000 50,000
3 Emergency Spillway Assume 100m length spillway with width of 3m and scour protection. 1,000 m2 20 20,000
4 Construction of Culvert Assume 40m length. Precast concrete culvert 2.4 x 2.4m 40 m 1,000 40,000
5 Landscaping / Reinstatement Spread and Rotivate topsoil, reseed locations and miscellaneous. Allow 2m storage depth at £1 per m2. 37,500 m2 1 37,500
6 Services interruption Depending on locations. Allow for utility company costs of £1000 per utility. Assume 3 utilities are affected. 3 Item 1,000 3,000





Construction Cost 900,500
7 General Contingency Allow 25% of Construction Cost


225,125
8 General and Preliminary Items Allow 25%


281,406
9 Overhead and Profit Allow 15%


211,055





Storage Reservoir Capital Works Cost 1,618,086
10 Reservoir Maintenance Supervising Engineer at £50 per hour for 2 days ( 7.5 hour day). 15 hours 50 750
11 Grass cutting of reservoir and maintenance of control structures Tractor with side arm cutter, plus one hand held strimmer for 5 days at £200 per day. Together with 2 Operatives at £12 per hour (7.5 hour day). 1 Item 1,900 1,900





Annual Post Construction Maintenance Cost 2,650
12 Design Design at 10% of Construction Cost and General contingency. Plus Panel engineer at £65 per hour for 2 weeks (7.5 hour day) 1 Item 117,438 117,438
13 Supervision Cost Full time supervisor at £35 per hour for 24 weeks (37.5 hour week) and Project Manager at £40 per hour for 22.5 hours per week. Plus Panel Engineer at £65 per hour for 2 weeks (37.5 hour week). 1 Item 45,375 45,375
14 Agency costs Project Manager at £40 per hour for 2 days (7.5 hour day) per week for 10 weeks 1 Item 6,000 6,000
15 Planning Supervisor Services Allowance of £6500 1 Item 6,500 6,500





Reservoir Design, Supervision and Agency Cost 175,313